ALMAL Real Estate Development has confirmed that construction of The Unexpected Al Marjan Island Hotel & Residences in Ras Al Khaimah has passed the halfway mark, with the project recording 50.82% completion in its latest RERA-certified update.
The beachfront development on Al Marjan Island is progressing towards its planned 2027 handover, according to the developer's November construction update.
The project is being developed by ALMAL Real Estate Development and managed by Palladium Hotel Group. Rising approximately 305 metres, the development comprises 319 hotel rooms and 103 branded residences, bringing its total inventory to 422 units.
Major structural works completed
According to the latest update, the building has reached its highest structural level, with reinforced concrete floor slabs completed across all levels. This marks the completion of the project's principal structural phase and allows construction teams to concentrate on the remaining building works.
Masonry blockwork and internal partitions have also been completed throughout the development, while plastering is nearing completion.
External façade and glazing installation are progressing, with work reported to have reached the sixth floor. These activities are taking place alongside the installation of building services and interior finishing works.
Mechanical and electrical installations advance
Mechanical, electrical and plumbing (MEP) work is continuing across the hotel and residential sections.
Electrical containment and cabling, air-conditioning systems and plumbing infrastructure have advanced to the seventh floor in apartment and corridor areas. ALMAL has also reported that most major mechanical equipment, including chillers and fresh air handling units, has been installed.
Interior fit-out work is underway in guest rooms, corridors and shared spaces. A completed sample guest room is being used as a benchmark for design details, materials, finishes and room layouts, helping guide the remaining interior work.
Developer maintains 2027 delivery target
Dmytro Starovoitov, founder of ALMAL Real Estate Development, described reaching more than 50% completion as an important step in the project's construction programme.
He emphasised that maintaining consistent progress, careful execution and attention to quality would be central to delivering the development. The company also reiterated that meeting its commitments to investors and future residents remains a priority.
ALMAL said it continues to focus on bringing together its architectural design, hospitality offering and beachfront residential concept as construction moves into its next stages.
Al Marjan Island's expanding hospitality and property landscape
The project forms part of the wider development activity taking place on Al Marjan Island, where new hospitality and residential schemes are contributing to Ras Al Khaimah's growing tourism and property market.
With its hotel operations supported by Palladium Hotel Group and a combination of hotel accommodation and branded residences, The Unexpected is positioned within the emirate's premium beachfront property segment.
The latest construction milestone provides an update on progress towards the scheduled 2027 handover. The developer's next challenge will be to complete the façade, building services and interior works while maintaining the quality and delivery schedule outlined in its latest announcement.